Renovation/Repair Pistol Range Marine Corps Logistics Base

Description

The renovation/ repair covered two major works, the modification of Berms and the installation of Bullet Trap. Six feet of imported 800 CY fine graded soil was added to extend the base of the berm approximately 6’ to the outside. A timber retaining wall, approximately 3’ high, was constructed on the inside to hold the added soil material. The Installation of the bullet trap required the removal of the existing lead contaminated berm, approximately 220 CY. After the berm was properly removed, the location of the bullet trap was graded and paved.

Information

Project Owner: United States Marine Corps Base
Client:
Yang | Martinez Joint Venture